After paying a progress draw, what release should the contractor provide for claimants paid for that portion of the work?
Correct Answer
B) An unconditional release signed by each claimant paid for the portion released.
CSLB guidance says that after payment, the contractor should provide an unconditional release signed by each claimant paid for the portion of the work being released.
Why This Is the Correct Answer
CSLB guidance says that after payment, the contractor should provide an unconditional release signed by each claimant paid for the portion of the work being released.
Why the Other Options Are Wrong
Option A: Release payment based only on the contractor's assurance where the file follows paying a progress draw, without verifying the claimant documents before payment.
Release payment based only on the contractor's assurance where the file follows paying a progress draw, without verifying the claimant documents before payment. skips the written authority, scope, price, notice, or release control needed for lien releases.
Option C: A new preliminary notice from every claimant already paid, and use that notice as the final payment release.
A new preliminary notice from every claimant already paid, and use that notice as the final payment release. skips the written authority, scope, price, notice, or release control needed for lien releases.
Option D: A verbal statement that all project parties are satisfied.
A verbal statement that all project parties are satisfied. skips the written authority, scope, price, notice, or release control needed for lien releases.
Memory Technique
When cslb clashes with guidance, let the contract speak before Closing Out.
Reference Hint
Study anchor (closed-book): memorize Lien releases from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code lien release forms; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
