EstatePass
Law & BusinessInsurance & Liensmedium12% of exam part

After paying a progress draw, what release should the contractor provide for claimants paid for that portion of the work?

Correct Answer

B) An unconditional release signed by each claimant paid for the portion released.

CSLB guidance says that after payment, the contractor should provide an unconditional release signed by each claimant paid for the portion of the work being released.

Answer Options
A
Release payment based only on the contractor's assurance where the file follows paying a progress draw, without verifying the claimant documents before payment.
B
An unconditional release signed by each claimant paid for the portion released.
C
A new preliminary notice from every claimant already paid, and use that notice as the final payment release.
D
A verbal statement that all project parties are satisfied.

Why This Is the Correct Answer

CSLB guidance says that after payment, the contractor should provide an unconditional release signed by each claimant paid for the portion of the work being released.

Why the Other Options Are Wrong

Option A: Release payment based only on the contractor's assurance where the file follows paying a progress draw, without verifying the claimant documents before payment.

Release payment based only on the contractor's assurance where the file follows paying a progress draw, without verifying the claimant documents before payment. skips the written authority, scope, price, notice, or release control needed for lien releases.

Option C: A new preliminary notice from every claimant already paid, and use that notice as the final payment release.

A new preliminary notice from every claimant already paid, and use that notice as the final payment release. skips the written authority, scope, price, notice, or release control needed for lien releases.

Option D: A verbal statement that all project parties are satisfied.

A verbal statement that all project parties are satisfied. skips the written authority, scope, price, notice, or release control needed for lien releases.

Memory Technique

When cslb clashes with guidance, let the contract speak before Closing Out.

Reference Hint

Study anchor (closed-book): memorize Lien releases from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code lien release forms; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.