A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
Correct Answer
A) Use a written home improvement contract before starting the work.
In California, a written contract is required for home improvement projects over $500.
Why This Is the Correct Answer
In California, a written contract is required for home improvement projects over $500.
Why the Other Options Are Wrong
Option B: Rely on a verbal agreement because the job is below $1,000, even after the owner has seen the finished repair.
Rely on a verbal agreement because the job is below $1,000, even after the owner has seen the finished repair. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option C: Use the material-order amount as the signing payment without applying the statutory contract limit.
Use the material-order amount as the signing payment without applying the statutory contract limit. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option D: Skip written terms if the work can be completed in one day.
Skip written terms if the work can be completed in one day. skips the written authority, scope, price, notice, or release control needed for project contracts.
Memory Technique
When business clashes with professions, let the controlling choice Deciding Whether.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
A company has annual overhead of $240,000 and expects 12,000 direct labor hours. What overhead rate per direct labor hour should be used?