Flooring is excluded in the written scope, but the owner says it was discussed during sales. What should resolve the issue?
Correct Answer
B) Written scope.
The written scope controls included work unless a written change modifies it.
Why This Is the Correct Answer
The written scope controls included work unless a written change modifies it.
Why the Other Options Are Wrong
Option A: Finish selection schedule.
Finish selection schedule. skips the written authority, scope, price, notice, or release control needed for scope dispute.
Option C: Specification sheet.
Specification sheet. skips the written authority, scope, price, notice, or release control needed for scope dispute.
Option D: Work sequence note.
Work sequence note. skips the written authority, scope, price, notice, or release control needed for scope dispute.
Memory Technique
When controlling clashes with controls, let the contract speak before Resolving Near.
Reference Hint
Study anchor (closed-book): memorize Scope dispute from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?