A Class B prime contract includes roofing, electrical, drywall, and concrete. What makes it fit the general building concept?
Correct Answer
B) It involves a structure and multiple unrelated building trades.
A general building project involves a structure and at least two unrelated building trades or crafts, subject to classification limits.
Why This Is the Correct Answer
A general building project involves a structure and at least two unrelated building trades or crafts, subject to classification limits.
Why the Other Options Are Wrong
Option A: Treat the work as allowed under the existing license where a Class B prime contract includes roofing, electrical, drywall, and concrete, without confirming the CSLB classification.
Treat the work as allowed under the existing license where a Class B prime contract includes roofing, electrical, drywall, and concrete, without confirming the CSLB classification. may relate to another site control, but it does not remove or guard the class b scope exposure being tested.
Option C: It includes any one specialty trade by itself.
It includes any one specialty trade by itself. may relate to another site control, but it does not remove or guard the class b scope exposure being tested.
Option D: It is allowed because the owner buys materials.
It is allowed because the owner buys materials. may relate to another site control, but it does not remove or guard the class b scope exposure being tested.
Memory Technique
Name the harm before the guard; treat, allowed, existing cannot stand in for Checking Multi-Trade.
Reference Hint
Study anchor (closed-book): memorize Class B scope from CSLB licensing classifications guidance; California Business and. / Business and Professions Code Section 7057; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?