A California Class B prime contract for a building remodel requires roofing, electrical, drywall and concrete work. Which feature supports the general-building classification’s multi-trade requirement?
Correct Answer
B) The structure requires at least two unrelated trades other than framing or carpentry.
The building project uses multiple unrelated trades beyond framing or carpentry. Section 7057(b) excludes framing and carpentry when counting the two unrelated trades for a project involving other trades. The listed roofing, electrical, drywall and concrete scopes support that test, subject to the remaining classification requirements. Owner-purchased materials alone do not establish the license scope. Source: https://www.cslb.ca.gov/Resources/GuidesAndPublications/2026/2026_CSLB_Law_Book.pdf
Why This Is the Correct Answer
The building project uses multiple unrelated trades beyond framing or carpentry. Section 7057(b) excludes framing and carpentry when counting the two unrelated trades for a project involving other trades. The listed roofing, electrical, drywall and concrete scopes support that test, subject to the remaining classification requirements. Owner-purchased materials alone do not establish the license scope. Source: https://www.cslb.ca.gov/Resources/GuidesAndPublications/2026/2026_CSLB_Law_Book.pdf
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Law & Business Questions
A contractor pays workers through a payment app but does not issue itemized pay statements. What is missing?
Apply California’s standard overtime rules, with no alternative-workweek or other exception. A nonexempt worker at a regular rate of $36 per hour works 15 hours in one day. What is the day's gross pay, ignoring weekly overtime?
A supplier delivers special-order windows to the site, but the contract does not list when material payments are due. What should be checked?
A site checklist requires 31 separate SDS records, one for each listed product. It contains 27 valid records corresponding to 27 different listed products, with no duplicates or shared SDS entries. How many required records are missing?
In the bathroom addition file, cash is $28,000, receivables are $44,000, inventory is $16,000, and current liabilities are $60,000. What is the quick ratio?
A worker requests their own payroll records, but the company says only managers may see them. What should be reviewed?
Special-order cabinets are stored at the supplier, but the contract only pays for materials delivered to the job. What should be checked?
A contractor is unsure whether a publicly funded building upgrade is public work. What is the best first step?
A contractor's workers' compensation certificate lists the policy number but omits effective and expiration dates. What is the problem?
A jobsite stores flammable liquid next to ignition sources and exits. What is the best correction?
People Also Study
Related Study Resources
Previous Question
Flooring is excluded in the signed written scope, but the owner recalls it being discussed during sales. Which document should first be reviewed to identify the recorded inclusion or exclusion?
Next Question
No exception applies to an employer’s IIPP inspection-record retention under section 3203(b)(1). Express its minimum one-year period in months.