A job used 72 equipment hours at an internal allocation rate of $18 per hour. What equipment cost should be charged to the job?

Correct Answer

D) $1,296.

Equipment allocation is 72 hours x $18 per hour = $1,296.

Answer Options
A
$12,960.
B
$130.
C
$90.
D
$1,296.

Why This Is the Correct Answer

Equipment allocation is 72 hours x $18 per hour = $1,296.

Why the Other Options Are Wrong

Option A: $12,960.

$12,960 misplaces the decimal point, giving ten times the correct amount. The correct calculation is 72 x 18 = 1,296.

Option B: $130.

$130 misplaces the decimal point, giving one tenth of the correct amount. The correct calculation is 72 x 18 = 1,296.

Option C: $90.

$90 adds 72 and 18 instead of multiplying. The correct calculation is 72 x 18 = 1,296.

Reference Hint

Study anchor (closed-book): memorize Equipment allocation from CSLB Law and Business Study Guide; CSLB 2026 Law Book / CSLB Law and Business Study Guide Business Finances; know the rule or calculation trigger without relying on exam-room lookup.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.