EstatePass
ca-law-businessBusiness Financesmedium

Base wages are $48,000 and employer payroll burden is estimated at 22 percent. What total labor cost should be budgeted?

Correct Answer

C) $58,560.

Payroll burden is $48,000 x 22 percent = $10,560. Total budgeted labor cost is $58,560.

Answer Options
A
$52,800.
B
$56,160.
C
$58,560.
D
$69,120.

Why This Is the Correct Answer

Payroll burden is $48,000 x 22 percent = $10,560. Total budgeted labor cost is $58,560.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.