Why can a longer development commitment require more total compensation to the developer, even when the annual required return is unchanged?
Correct Answer
C) Longer projects carry more risk and tie up capital
A longer commitment delays receipts and exposes capital to additional uncertainty. Market participants may require compensation through total return, cash-flow allowances or a risk-appropriate rate. Duration alone does not mandate a higher annual yield or a fixed profit percentage.
Why This Is the Correct Answer
Option C is correct because a longer commitment delays receipts and keeps capital exposed to risk for more time. Investors require a rate of return commensurate with the risk or uncertainty they assume, so more time at risk can require more total compensation. That compensation may appear as total return, cash-flow allowances or a risk-appropriate rate.
Why the Other Options Are Wrong
Option A: Construction costs rise each year over the project
Option A says construction costs rise each year over the project. Cost escalation is a separate cost issue and does not explain why the same annual return produces more total compensation over a longer period.
Option B: Lenders require a fixed share of gross revenue
Option B says lenders require a fixed share of gross revenue. That is not a standard reason; developer compensation reflects the capital committed and the risk taken over time.
Option D: Profit is set by statute according to project length
Option D says profit is set by statute according to project length. Developer profit is a market-derived expectation, not a statutory amount.
More time, more at stake
The longer money is tied up and exposed to risk, the more total return investors need. The annual rate can stay the same while the total grows.
How to use: Use this when a question links project length to developer profit.
Exam Tip
Separate the annual rate of return from total compensation; a longer period can raise the total without changing the rate.
Common Mistakes to Avoid
- -Confusing cost escalation with return on capital
- -Assuming a longer project requires a higher annual rate
- -Treating developer profit as a fixed legal percentage
Concept Deep Dive
Analysis
This question tests why project duration affects total developer compensation. Even if the annual required return is unchanged, a longer project ties up capital for more periods and exposes it to more uncertainty. Total compensation therefore can rise with duration.
Background Knowledge
Entrepreneurial incentive and developer profit compensate for the time, effort and risk of a project. Because returns are earned per period, capital committed over a longer period earns more total return even at the same annual rate, and longer projects may also carry more uncertainty.
Real-World Application
An appraiser compares two subdivision projects with similar annual return expectations, one selling out in two years and one in five years. The appraiser recognizes that the longer project needs more total compensation for the developer because capital is tied up longer and faces more market uncertainty.
More Land/Site Questions
How should an appraiser account for a site's access to public sewer compared with competing sites that require septic systems?
Which fact, if supported by competitive-market evidence, most directly supports a unit-price premium for an otherwise comparable site?
A rectangular site's frontage is doubled while its depth is halved, keeping area constant. What is the likely value effect in a retail district?
A downtown site's zoning height limit is reduced from six stories to three. Buyers in this market had been paying for six-story development potential. What effect on land value is most supportable?
A zoning change increases permitted density from four to eight units per acre. What is the likely effect on site value?
Using the allocation method, market evidence supports a typical land-to-total-property-value ratio of 28% for similar improved properties in the subject’s location. An improved comparable sold for $825,000. What land (site) contribution is indicated by applying that ratio?
An appraiser is valuing a vacant site near a landfill. A similar vacant site that is not affected by the landfill sold for $480,000. Paired land sales indicate that proximity to the landfill lowers site prices by $70,000. No other adjustments apply. What is the indicated value of the subject site?
An appraiser is extracting site value from a $600,000 cash sale. The seller's records show an original construction cost of $250,000 and a depreciated book value of $110,000. The appraiser estimates current replacement cost new at $400,000 and accrued depreciation from all causes at $100,000. What is the indicated site value?
Three parcels assembled under single ownership (standard appraisal guidance assemblage) support separate as-is values of $290,000, $340,000, and $250,000. After assemblage for a higher-utility use, the combined site is valued at $1,050,000. Assemblage costs (demolition, legal, holding, and related) total $55,000. What is the indicated net plottage (plottage increment after assemblage costs)?
A comparable commercial site with 65 front feet sold for a cash-equivalent price of $585,000. Per standard appraisal guidance, sale price per front foot is a vacant-land unit of comparison when frontage is a primary value determinant. The subject site has 72 front feet and is otherwise similar. What indicated land value does the front-foot unit support before other adjustments?
People Also Study
Real Estate Market
13.6% of exam
Property Description
11.8% of exam
Sales Comparison Approach
16.4% of exam
Cost Approach
13.6% of exam
Income Approach
8.2% of exam
Previous Question
A residential site adjoins a rendering plant. How should the effect be measured?
Next Question
Vacant land may be valued by a multi-comparable mean unit price ($/front foot) applied to the subject’s street frontage. Four similar vacant comps support unit prices of $2,500, $2,700, $2,900, and $3,100 per front foot. Subject has 160 front feet. What indicated land value by mean $/FF results?
