When replacement cost (not reproduction cost) is the basis, which functional obsolescence largely disappears from the estimate?

Correct Answer

B) The cost of superadequacies, which a replacement would not include

Why this is correct: Replacement cost estimates the cost to build a structure of equivalent utility using modern materials and design. Superadequacies (overbuilt features) are not included in this new design, so their excess cost is never incurred and need not be deducted. Why the other choices are wrong: "Deficiencies that the market would ordinarily expect to be cured" is wrong because a replacement building might still have deficiencies if not redesigned to market standards. "All functional obsolescence of every kind" is wrong because deficiencies and layout problems may still exist. "Obsolescence from an outdated floor plan" is wrong because the replacement might replicate an outdated plan unless redesigned. Exam tip: Replacement cost = modern equivalent utility. Superadequacies vanish because you wouldn't build them in.

Answer Options
A
Deficiencies that the market would ordinarily expect to be cured
B
The cost of superadequacies, which a replacement would not include
C
All functional obsolescence of every kind
D
Obsolescence from an outdated floor plan

Why This Is the Correct Answer

Why this is correct: Replacement cost estimates the cost to build a structure of equivalent utility using modern materials and design. Superadequacies (overbuilt features) are not included in this new design, so their excess cost is never incurred and need not be deducted. Why the other choices are wrong: "Deficiencies that the market would ordinarily expect to be cured" is wrong because a replacement building might still have deficiencies if not redesigned to market standards. "All functional obsolescence of every kind" is wrong because deficiencies and layout problems may still exist. "Obsolescence from an outdated floor plan" is wrong because the replacement might replicate an outdated plan unless redesigned. Exam tip: Replacement cost = modern equivalent utility. Superadequacies vanish because you wouldn't build them in.

Was this explanation helpful?

More Cost Approach Questions

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing