A development budget consists of direct costs of $720,000, indirect costs of $95,000, site cost of $180,000 and a separate entrepreneurial incentive of $85,000, with no overlap among them. What is the total development cost, including the site?

Correct Answer

C) $1,080,000

720000+95000+180000+85000 = 1080000. Common errors: leaving out the indirect costs gives $985,000; leaving out the entrepreneurial incentive gives $995,000; counting the site twice gives $1,260,000.

Answer Options
A
$985,000
B
$995,000
C
$1,080,000
D
$1,260,000

Why This Is the Correct Answer

Option C is correct because development cost includes all direct and indirect costs plus the cost of the land and the entrepreneurial profit. $720,000 + $95,000 + $180,000 + $85,000 = $1,080,000. Each component is nonoverlapping, so each is counted once.

Why the Other Options Are Wrong

Option A: $985,000

Option A, $985,000, is $720,000 + $180,000 + $85,000, which leaves out the $95,000 of indirect costs. Including them gives $1,080,000.

Option B: $995,000

Option B, $995,000, is $720,000 + $95,000 + $180,000, which leaves out the $85,000 entrepreneurial incentive. Including it gives $1,080,000.

Option D: $1,260,000

Option D, $1,260,000, is $720,000 + $95,000 + ($180,000 x 2) + $85,000, which counts the site twice. The site is included once, for $1,080,000.

Development cost includes dirt

Development cost is everything: direct, indirect, land and profit. Improvement cost leaves the land out.

How to use: Use this to decide whether site value belongs in a cost total.

Exam Tip

Look for words like all-in or development cost, which signal that land is included. Count each component exactly once.

Common Mistakes to Avoid

  • -Leaving land out of a development cost total
  • -Omitting entrepreneurial incentive
  • -Counting the land cost twice

Concept Deep Dive

Analysis

This question tests the definition of development cost, which differs from improvement-only cost because it includes land. Development cost is the all-inclusive total of direct costs, indirect costs, land and entrepreneurial profit. Add each of the four stated pieces once.

Background Knowledge

Development cost is the all-inclusive cost to develop a property, including direct and indirect costs, land cost and entrepreneurial profit. Improvement cost new, by contrast, excludes land. Knowing which total a question asks for decides whether site value is part of the sum.

Real-World Application

A builder asks an appraiser to compare the total cost of building a speculative house with its expected market value. The appraiser sums lot acquisition, construction costs, soft costs and a market-supported builder's incentive to estimate total development cost.

development costland costentrepreneurial incentiveindirect costsdirect costs
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing