EstatePass
Cost ApproachMEDIUM13.6% of exam

Installed direct construction costs of the improvements total $400,000. Indirect costs of $60,000 are not included in that figure, and together the two amounts cover all required cost components. Land is excluded. What is the full cost new of the improvements?

Correct Answer

D) $460,000

400000+60000 = 460000. Common errors: leaving out the indirect costs gives $400,000; subtracting the indirect costs instead of adding them gives $340,000; treating the $60,000 as 6% of the base gives $424,000.

Answer Options
A
$340,000
B
$400,000
C
$424,000
D
$460,000

Why This Is the Correct Answer

Option D is correct because full improvement cost must account for all direct and indirect costs. The $60,000 of indirect costs is explicitly not in the $400,000 direct base, so $400,000 + $60,000 = $460,000. With all required components covered and land excluded, that is the full cost new.

Why the Other Options Are Wrong

Option A: $340,000

Option A, $340,000, is $400,000 - $60,000, which subtracts the indirect costs instead of adding them. Indirect costs are part of cost, so the total is $460,000.

Option B: $400,000

Option B, $400,000, reports the direct costs alone and leaves out the $60,000 of indirect costs. Full cost new is $460,000.

Option C: $424,000

Option C, $424,000, is $400,000 x 1.06, which treats the $60,000 as 6% of the base. The indirect cost is a stated $60,000 dollar amount, so the total is $460,000.

Indirect costs add on

Indirect costs are real costs of building, so they are added to direct costs, not subtracted.

How to use: Use this when a question gives direct costs and separately stated indirect costs.

Exam Tip

Read whether an indirect cost is given as a dollar amount or a percentage before computing. Confirm it is not already embedded in the base.

Common Mistakes to Avoid

  • -Omitting indirect costs from cost new
  • -Subtracting indirect costs instead of adding them
  • -Treating a dollar amount as a percentage

Concept Deep Dive

Analysis

This question tests adding separate indirect costs to direct costs to reach full improvement cost new. The $60,000 is stated as a dollar amount not included in the base, so it is added once. Land is excluded.

Background Knowledge

Indirect costs such as fees, permits, insurance and financing during construction are part of the cost of producing an improvement. When a cost source excludes them, the appraiser adds them separately. Full cost new of improvements excludes land value.

Real-World Application

An appraiser uses a cost manual that reports direct building costs only. The appraiser adds permit fees, architectural fees and construction loan interest as indirect costs to reach full cost new before estimating depreciation.

indirect costsdirect costscost newsoft costscost approach
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing