Cost ApproachMEDIUM13.6% of exam

Nonoverlapping improvement costs are direct $385,000, indirect $55,000 and a separately supported entrepreneurial incentive $72,000 not otherwise included. Land is excluded. What full cost new results?

Correct Answer

D) $512,000

385000+55000+72000 = 512000. Common errors: leaving out the entrepreneurial incentive gives $440,000; leaving out the indirect costs gives $457,000; reporting only the direct costs gives $385,000.

Answer Options
A
$385,000
B
$440,000
C
$457,000
D
$512,000

Why This Is the Correct Answer

Option D is correct because full economic cost includes all direct and indirect costs plus market-supportable entrepreneurial profit. The three nonoverlapping pieces add to $385,000 + $55,000 + $72,000 = $512,000. Land is excluded, so nothing else is added.

Why the Other Options Are Wrong

Option A: $385,000

Option A, $385,000, reports only the direct costs. Full cost also requires the $55,000 of indirect costs and the $72,000 incentive, for $512,000.

Option B: $440,000

Option B, $440,000, is $385,000 + $55,000, which leaves out the $72,000 entrepreneurial incentive. Including it gives $512,000.

Option C: $457,000

Option C, $457,000, is $385,000 + $72,000, which leaves out the $55,000 of indirect costs. Including all three pieces gives $512,000.

Direct plus indirect plus incentive

Full cost new stacks three layers: direct, indirect and supported entrepreneurial incentive. Drop any layer and the total is too low.

How to use: Use this three-layer check whenever a question asks for full cost new of improvements.

Exam Tip

Note whether land is excluded or included; improvement-only cost leaves out site value. Each wrong option here drops one of the three layers.

Common Mistakes to Avoid

  • -Leaving out entrepreneurial incentive when it is supported
  • -Forgetting indirect costs such as fees and financing
  • -Adding land value to an improvement-only cost

Concept Deep Dive

Analysis

This question tests the components of full cost new for improvements. Full cost includes direct costs, indirect costs and a supported entrepreneurial incentive when not already included. Land is excluded, so the answer is the sum of the three improvement cost pieces.

Background Knowledge

Direct (hard) costs are the labor, materials and contractor costs of construction, and indirect (soft) costs include items such as fees, financing and insurance. Entrepreneurial incentive is the market-supported reward a developer expects for taking on the project. Together these make up full cost new of the improvements.

Real-World Application

An appraiser estimating cost new for a newly built custom house gathers contractor bids for direct costs, adds design fees and construction loan interest as indirect costs, and adds a builder incentive supported by recent projects in the market.

full cost newdirect costsindirect costsentrepreneurial incentivecost approach
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing