Cost ApproachMEDIUM13.6% of exam

Direct costs including contractor overhead/profit are $420,000. Additional indirect costs are $65,000 and separately supported entrepreneurial incentive $55,000, not already counted. Land is separate and excluded from this question. What improvement cost new results?

Correct Answer

D) $540,000

420000+65000+55000 = 540000. Common errors: leaving out the entrepreneurial incentive gives $485,000; leaving out the indirect costs gives $475,000; reporting only the direct costs gives $420,000.

Answer Options
A
$420,000
B
$475,000
C
$485,000
D
$540,000

Why This Is the Correct Answer

Option D is correct because $420,000 + $65,000 + $55,000 = $540,000. Contractor overhead and profit are already inside the direct costs, while the indirect costs and the entrepreneurial incentive are not already counted. Full economic cost includes all three, and land is not part of improvement cost.

Why the Other Options Are Wrong

Option A: $420,000

Option A is wrong because $420,000 reports only the direct costs. Adding the $65,000 indirect costs and $55,000 incentive gives $540,000.

Option B: $475,000

Option B is wrong because $475,000 leaves out the indirect costs: $420,000 + $55,000 = $475,000. Adding the $65,000 indirect costs gives $540,000.

Option C: $485,000

Option C is wrong because $485,000 leaves out the entrepreneurial incentive: $420,000 + $65,000 = $485,000. Adding the separately supported $55,000 gives $540,000.

Contractor profit is direct

Contractor profit sits inside direct costs; developer incentive is a separate layer added on top.

How to use: Use this when a question mentions both contractor profit and entrepreneurial incentive.

Exam Tip

Do not confuse contractor's overhead and profit with entrepreneurial incentive. They are different and can both belong in full cost.

Common Mistakes to Avoid

  • -Treating contractor profit and entrepreneurial incentive as the same thing
  • -Leaving out indirect costs
  • -Including land value in improvement cost new

Concept Deep Dive

Analysis

This question tests building full improvement cost new from components. Direct costs already include contractor overhead and profit, so only the indirect costs and separately supported entrepreneurial incentive are added. The total is $420,000 + $65,000 + $55,000 = $540,000, with land excluded.

Background Knowledge

Contractor's overhead and profit is a direct cost, while entrepreneurial profit is a separate return to the developer for expertise and risk. Full economic cost includes direct costs, indirect costs and market-supportable entrepreneurial profit.

Real-World Application

A builder's bid of $420,000 includes the contractor's markup, and the appraiser adds $65,000 of soft costs and a $55,000 market-supported developer incentive. The resulting $540,000 is the improvement cost new before depreciation and site value.

direct costscontractor overhead and profitindirect costsentrepreneurial incentivecost new
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing