Direct and indirect costs total $340,000 and entrepreneurial incentive in this market is 12% of those costs. What is the total cost new?

Correct Answer

C) $380,800

Why this is correct: entrepreneurial incentive is what a developer must expect to earn for the project to be built at all, and it is part of cost new. Calculation: $340,000 x 1.12 = $380,800. Why the other choices are wrong: $340,000 omits the incentive; $385,000 follows from neither figure; $40,800 is the incentive alone rather than the total it belongs to.

Answer Options
A
$340,000
B
$385,000
C
$380,800
D
$40,800

Why This Is the Correct Answer

Why this is correct: entrepreneurial incentive is what a developer must expect to earn for the project to be built at all, and it is part of cost new. Calculation: $340,000 x 1.12 = $380,800. Why the other choices are wrong: $340,000 omits the incentive; $385,000 follows from neither figure; $40,800 is the incentive alone rather than the total it belongs to.

Was this explanation helpful?

More Cost Approach Questions

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing