EstatePass
Cost ApproachMEDIUM13.6% of exam

A cost service quotes a base for a different documented date and location. How should it be adapted?

Correct Answer

C) Apply supported date and location adjustments, without double counting.

Review the service’s date, location and coverage, then apply only supported necessary adjustments. A current locally calibrated base may need no additional multiplier; do not adjust twice. Remote construction is not automatically cheaper, and unit conversions depend on actual units.

Answer Options
A
Do not adjust a national base, because it is authoritative.
B
Deduct for a rural location, because remote construction is assumed to be cheaper.
C
Apply supported date and location adjustments, without double counting.
D
Convert the base to metric units before applying it.

Why This Is the Correct Answer

Option C is correct because building costs are constantly changing and differ by market, so a base quoted for another date and location must be brought to the subject's date and area with supported multipliers. The appraiser should verify what the data already includes so that no adjustment is applied twice.

Why the Other Options Are Wrong

Option A: Do not adjust a national base, because it is authoritative.

Option A says not to adjust a national base because it is authoritative. A published base still reflects a specific date and cost level, so it needs supported adjustments when the subject's date or location differs.

Option B: Deduct for a rural location, because remote construction is assumed to be cheaper.

Option B says to deduct for a rural location because remote construction is assumed cheaper. Remote construction is not automatically cheaper and can cost more because of travel, labor and material delivery, so any location adjustment needs support.

Option D: Convert the base to metric units before applying it.

Option D says to convert the base to metric units before applying it. Unit conversion depends on the units actually used and does nothing to address the date and location differences in the question.

When and Where

A cost base has a when and a where. Fix both with supported multipliers, and fix each only once.

How to use: Use this check whenever a cost-service figure comes from a different date or market.

Exam Tip

Prefer answers that call for supported adjustments and warn against double counting over answers that assume a fixed direction for location.

Common Mistakes to Avoid

  • -Applying a local multiplier to a base already calibrated for that market
  • -Assuming rural construction always costs less
  • -Using an outdated cost base without a time adjustment

Concept Deep Dive

Analysis

This question tests how to adapt cost-service data to the subject's date and location. Building costs change over time and vary by area, so a base for another date and location needs supported adjustments. The appraiser must also avoid applying the same adjustment twice.

Background Knowledge

Cost manuals typically provide time multipliers to update costs and local multipliers to reflect regional cost differences. A base already calibrated to the current date and local market may need no further multiplier, so the appraiser reviews the service's coverage before adjusting.

Real-World Application

An appraiser pulls a base cost from a manual dated several months before the effective date. She applies the manual's current time multiplier and the local multiplier for the subject's county, after confirming the base was not already locally adjusted.

cost servicetime multiplierlocation multiplierdouble countingcost new
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing