The current cost of a building is estimated at $62 per square foot for 3,000 square feet. Site improvements not already included in that figure would cost an additional $45,000. What is the total cost of the improvements, excluding land and any other additions?
Correct Answer
C) $231,000
3000×62+45000 = 231000. Common errors: leaving out the site-improvement cost gives $186,000; subtracting the site-improvement cost instead of adding it gives $141,000; counting the building cost twice gives $417,000.
Why This Is the Correct Answer
Option C is correct because 3,000 sf x $62/sf = $186,000 for the building, and adding the separate $45,000 site-improvement cost gives $186,000 + $45,000 = $231,000. The site improvements are not embedded in the square-foot price, so they belong in the improvement subtotal exactly once.
Why the Other Options Are Wrong
Option A: $141,000
Option A, $141,000, comes from subtracting the site-improvement cost instead of adding it: $186,000 - $45,000 = $141,000. Site improvements add cost, so the correct subtotal is $186,000 + $45,000 = $231,000.
Option B: $186,000
Option B, $186,000, is only the building cost (3,000 x $62) and leaves out the $45,000 site-improvement cost that the facts say is not already included. Adding it gives $231,000.
Option D: $417,000
Option D, $417,000, counts the building cost twice: 2 x $186,000 + $45,000 = $417,000. The building is counted once, giving $186,000 + $45,000 = $231,000.
Area times rate, plus extras
First multiply area by the unit rate, then add each separately stated item once. Anything already included in the rate is not added again.
How to use: Use this whenever a cost question lists a unit price plus separately stated components.
Exam Tip
Read whether each extra cost is already included in the unit price; the wording 'not already included' tells you to add it once.
Common Mistakes to Avoid
- -Reporting only the building cost and forgetting separately stated site improvements
- -Counting the building cost twice
- -Subtracting an added cost item instead of adding it
Concept Deep Dive
Analysis
This question tests building a simple improvement cost subtotal from a square-foot cost plus a separate site-improvement cost. The building cost is area times unit cost, and the site improvements are stated as not already included, so they must be added once. Land is expressly outside the requested subtotal.
Background Knowledge
In the square-foot (comparative unit) method, the construction costs covered by a unit rate are expressed as a price per square foot and applied to the subject's area. Items not captured in that unit price, such as separately costed site improvements, are added once so that all direct and indirect costs of the improvements are accounted for without double counting.
Real-World Application
An appraiser prices a 3,000 sf dwelling from a cost manual at a per-square-foot rate that covers the building shell and finishes. The driveway, walks and landscaping are costed separately and added to reach the improvement subtotal before considering depreciation and land.
More Cost Approach Questions
Why can equivalent-utility replacement cost be useful for an obsolete improvement?
An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?
Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?
What best supports a claimed loss from a bathroom-layout deficiency?
Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?
Which scenario most strongly supports giving the cost approach substantial weight?
A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?
A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?
A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?
An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?
People Also Study
Real Estate Market
13.6% of exam
Property Description
11.8% of exam
Land or Site Valuation
4.5% of exam
Sales Comparison Approach
16.4% of exam
Income Approach
8.2% of exam
Previous Question
An appraiser estimates replacement cost using a national cost-estimating service. What should the appraiser make sure of?
Next Question
The historical cost of a structure was $380,000, and a suitable index multiplier for the same construction scope is 1.40. Total depreciation of the improvements is $95,000, and site value is $175,000. What is the indicated value?
