Reliable engineering shows that a 10-acre site has a maximum physical capacity of 3 units per acre over the whole site. Zoning permits 4 units per acre, and no other constraint applies. What is the maximum number of units physically possible on the site?
Correct Answer
B) 30 units (3 × 10)
The physical cap gives 10×3=30 units. The separate zoning allowance would permit 40 units but does not increase engineering capacity. Averaging to 35 has no basis. Legal permissibility and physical possibility are different criteria; neither this unit count nor meeting both caps alone establishes financial feasibility or maximum productivity.
Why This Is the Correct Answer
Option B is correct because the physical cap is 3 units per acre × 10 acres = 30 units. Zoning permits 4 units per acre, but legal permission does not raise the engineering capacity. The physical limit therefore controls the maximum unit count asked for.
Why the Other Options Are Wrong
Option A: Cannot be determined from the facts
Option A, cannot be determined from the facts, is wrong because the stem gives both the site area and the physical density, so 10 × 3 = 30 units is directly calculable.
Option C: 35 units (average of 3 and 4 × 10)
Option C, 35 units, averages the two densities ((3 + 4) ÷ 2 × 10 = 35), which has no basis; the physical cap gives 10 × 3 = 30 units.
Option D: 40 units (4 × 10)
Option D, 40 units, uses the zoning density (4 × 10 = 40), but the question asks what follows from the physical cap, which is 10 × 3 = 30 units.
The tighter limit wins
When legal and physical limits differ, the lower one caps what can actually be built.
How to use: Use this when a question gives both a zoning density and a physical capacity.
Exam Tip
Do not average competing limits; identify which constraint the question asks about or which one binds.
Common Mistakes to Avoid
- -Using the zoning density when the physical cap is lower
- -Averaging legal and physical densities
- -Assuming a unit count that meets both caps is automatically financially feasible
Concept Deep Dive
Analysis
This question tests the difference between what is legally permitted and what is physically possible. Zoning allows 40 units, but engineering limits the site to 30 units. The question asks for the count that follows from the physical cap, so multiply the physical density by the site area.
Background Knowledge
Highest and best use analysis tests whether a use is legally permissible, physically possible, financially feasible and maximally productive. A use must pass each test, so the more restrictive of the legal and physical limits sets the practical density, and financial feasibility still requires separate analysis.
Real-World Application
A developer assumes zoning allows 40 homes on a 10-acre tract, but soils and drainage engineering support only 30. The appraiser's highest and best use analysis uses the 30-unit physical capacity and then tests whether that project is financially feasible.
More Property Description Questions
Market analysis confirms that seller financing at 3%, versus a 6% market rate, increased a comparable sale price. What adjustment removes that financing premium?
At the same effective date, reliable value indications support $800,000 for continued use of a property as improved and $500,000 for its cleared site. Immediate demolition costs $100,000. These are the only feasible alternatives, with no other costs or timing differences. Which alternative has the higher net value?
Other relevant conditions equal, growth in the number of households with effective purchasing power in a market tends to have which effect?
In a lakefront market, paired sales show that direct water frontage has the largest price effect of any feature. Which approach to comparable selection best follows from this evidence?
Which circumstance can cause highest and best use as improved to differ from highest and best use as though vacant?
A small group of buyers in a market looks for specialized features that are uncommon in the broader housing supply. What term describes this group?
A neighborhood analysis should include all of the following EXCEPT:
A site legally permits at most 40 units and can physically support 50. Supported comparable analyses find 30 and 40 units financially feasible, with 40 units producing the highest net land value after costs, timing and required return. Which use is maximally productive among these alternatives?
Market evidence isolates a subject value loss from off-site landfill odors. Which listed cause is an external-obsolescence influence?
Which proposed use cannot pass the legal-permissibility screen without evidence that the necessary permission is reasonably probable?
People Also Study
Real Estate Market
13.6% of exam
Land or Site Valuation
4.5% of exam
Sales Comparison Approach
16.4% of exam
Cost Approach
13.6% of exam
Income Approach
8.2% of exam
