Under California's Permit Streamlining Act, a local agency must approve or deny a development project application within specified timeframes. If the agency fails to act within the deadline for a project that requires an EIR, what happens?

Correct Answer

A) The project is automatically approved by operation of law

Government Code 65956(b) provides that when a lead agency or responsible agency fails to approve or disapprove a development project within the time limits of the Permit Streamlining Act, the failure to act is deemed approval of the permit application. For a project requiring an environmental impact report, the decision period runs from certification of the report, so missing that deadline produces a deemed approval by operation of law. The version of §65956(b) enacted by 2025 AB 130 (Chapter 22) does not state prior public notice as a separate condition of deemed approval; subdivision (d) separately preserves applicable agency notice and hearing responsibilities. The governing version and the actual applicable decision clock must be established for the project. Section 65956(a) separately allows a writ action under Code of Civil Procedure 1085 to compel the agency to give the notice or hold the hearing.

Answer Options
A
The project is automatically approved by operation of law
B
The project application is automatically denied
C
The deadline is extended by an additional 180 days
D
The applicant may file a court action to compel the agency to act, but the project is not automatically approved

Why This Is the Correct Answer

Government Code 65956(b) provides that when a lead agency or responsible agency fails to approve or disapprove a development project within the time limits of the Permit Streamlining Act, the failure to act is deemed approval of the permit application. For a project requiring an environmental impact report, the decision period runs from certification of the report, so missing that deadline produces a deemed approval by operation of law. The version of §65956(b) enacted by 2025 AB 130 (Chapter 22) does not state prior public notice as a separate condition of deemed approval; subdivision (d) separately preserves applicable agency notice and hearing responsibilities. The governing version and the actual applicable decision clock must be established for the project. Section 65956(a) separately allows a writ action under Code of Civil Procedure 1085 to compel the agency to give the notice or hold the hearing.

Why the Other Options Are Wrong

Deep Analysis of This Property Ownership Land Use Controls Question

Background Knowledge for Property Ownership Land Use Controls

Memory Technique

Exam Tip for Property Ownership Land Use Controls

Real World Application in Property Ownership Land Use Controls

Common Mistakes to Avoid on Property Ownership Land Use Controls Questions

Related Topics & Key Terms

Key Terms:

Permit_Streamlining_Actagency_deadlineswrit_of_mandateEIR

Related Concepts

An easement by necessity is created by court order when a property is landlocked and has no access to a public road. It arises from the necessity of accessing the property, not from long-term use.

An easement by prescription is acquired through continuous, open, notorious, hostile, and uninterrupted use of another's land for a statutory period. It is similar to adverse possession but grants use rights, not ownership.

Eminent domain is the government's constitutional right to take private property for public use, provided the owner receives just compensation. It is also known as condemnation.

Was this explanation helpful?

More Property Ownership Land Use Controls Questions

People Also Study

Related Articles

Practice More Questions

Access 2,000+ practice questions and pass your real estate exam.

Start Practicing