Property Ownership Land Use ControlsEncumbrances_and_liensMEDIUM

A general contractor in California completes a home addition on June 15. The homeowner records a notice of completion on June 20. Under California mechanics' lien law, what is the deadline for the general contractor to record a mechanics' lien?

Correct Answer

D) 60 days after the notice of completion is recorded (August 19)

Under California Civil Code §8412, a direct (general) contractor must record a mechanics' lien within 60 days after the owner records a notice of completion. The notice of completion was recorded on June 20, so the general contractor has until August 19. Note: if no notice of completion is recorded, the direct contractor's deadline is 90 days after actual completion of the work of improvement.

Answer Options
A
30 days after the notice of completion is recorded (July 20)
B
90 days after the actual completion of the project (September 13)
C
60 days after the actual completion of the project (August 14)
D
60 days after the notice of completion is recorded (August 19)

Why This Is the Correct Answer

Sign up free to unlock full analysis

Why the Other Options Are Wrong

Sign up free to unlock full analysis

Deep Analysis of This Property Ownership Land Use Controls Question

Sign up free to unlock full analysis

Background Knowledge for Property Ownership Land Use Controls

Sign up free to unlock full analysis
Sign up free to unlock full analysis

Real World Application in Property Ownership Land Use Controls

Sign up free to unlock full analysis

Common Mistakes to Avoid on Property Ownership Land Use Controls Questions

Sign up free to unlock full analysis

Related Topics & Key Terms

Key Terms:

mechanics_liengeneral_contractornotice_of_completion60_day_deadlineCivil_Code_8412
Was this explanation helpful?

More Property Ownership Land Use Controls Questions

People Also Study

Practice More Questions

Access 2,000+ practice questions and pass your real estate exam.

Start Practicing