A general contractor in California completes a home addition on June 15. The homeowner records a notice of completion on June 20. Under California mechanics' lien law, what is the deadline for the general contractor to record a mechanics' lien?

Correct Answer

D) 60 days after the notice of completion is recorded (August 19)

Under California Civil Code §8412, a direct (general) contractor must record a mechanics' lien within 60 days after the owner records a notice of completion. The notice of completion was recorded on June 20, so the general contractor has until August 19. Note: if no notice of completion is recorded, the direct contractor's deadline is 90 days after actual completion of the work of improvement.

Answer Options
A
30 days after the notice of completion is recorded (July 20)
B
90 days after the actual completion of the project (September 13)
C
60 days after the actual completion of the project (August 14)
D
60 days after the notice of completion is recorded (August 19)

Why This Is the Correct Answer

Under California Civil Code §8412, a direct (general) contractor must record a mechanics' lien within 60 days after the owner records a notice of completion. The notice of completion was recorded on June 20, so the general contractor has until August 19. Note: if no notice of completion is recorded, the direct contractor's deadline is 90 days after actual completion of the work of improvement.

Interactive lesson · Chapter 21 of 30 · Liens and foreclosure

Kinds of liens

A lien is voluntary when the owner creates it (a mortgage) and involuntary when the law imposes it (taxes, mechanic's liens, judgments). It is specific when it attaches to one property and general when it reaches all of the debtor's property.

Voluntary · specificInvoluntary · specificInvoluntary · generalNot a lien
Voluntary: the owner creates it (a mortgage)Involuntary: the law creates it (taxes, mechanic's, judgment)Specific: one property; general: all the debtor's propertyEvery lien is an encumbrance; not every encumbrance is a lien
Voluntary or involuntary; specific or general

Chapters 1–3 are free in full, practice sets included.

Why the Other Options Are Wrong

Deep Analysis of This Property Ownership Land Use Controls Question

Background Knowledge for Property Ownership Land Use Controls

Memory Technique

Exam Tip for Property Ownership Land Use Controls

Real World Application in Property Ownership Land Use Controls

Common Mistakes to Avoid on Property Ownership Land Use Controls Questions

Related Topics & Key Terms

Key Terms:

mechanics_liengeneral_contractornotice_of_completion60_day_deadlineCivil_Code_8412

Related Concepts

Deed restrictions are limitations placed in a deed that control how a property may be used by the current and future owners. They are a form of private land use control that runs with the land.

An easement is a legal right to use another person's land for a specific purpose without owning it. It is a nonpossessory interest in real property that typically runs with the land.

An easement by necessity is created by court order when a property is landlocked and has no access to a public road. It arises from the necessity of accessing the property, not from long-term use.

Was this explanation helpful?

More Property Ownership Land Use Controls Questions

People Also Study

Related Articles

Practice More Questions

Access 2,000+ practice questions and pass your real estate exam.

Start Practicing