1. Approved switchgear has a lead time longer than the current installation milestone. What is the best first project-control response?
- AHide the lead time until the milestone is missed
- BOrder unapproved equipment with no submittal
- CRemove testing activities to recover every lost day
- Document constraints and update project logic
Why D is correct
A long-lead constraint belongs in the risk, procurement, and schedule processes. The manager should surface it, evaluate compliant mitigation, obtain approvals, and update dependencies; concealment or unauthorized substitution creates larger technical and contractual failures.