Project Design & ManagementNASCLA Electrical Practice Questions

12 questions · 8% of the NASCLA Electrical exam

Worked questions

1. Approved switchgear has a lead time longer than the current installation milestone. What is the best first project-control response?

  • AHide the lead time until the milestone is missed
  • BOrder unapproved equipment with no submittal
  • CRemove testing activities to recover every lost day
  • Document constraints and update project logic

Why D is correct

A long-lead constraint belongs in the risk, procurement, and schedule processes. The manager should surface it, evaluate compliant mitigation, obtain approvals, and update dependencies; concealment or unauthorized substitution creates larger technical and contractual failures.

2. The owner verbally requests additional receptacles after rough-in begins. What protects the project most effectively?

  • ARefuse to record the request
  • BCharge the field crew personally
  • Get written change authorization
  • DPerform the work and hope it is paid

Why C is correct

A verbal request should enter the project change-control process. Scope, price, schedule, and authority must be documented under the contract so the owner understands the impact and the contractor preserves entitlement; undocumented work is a classic dispute source.

3. A repeated torque-inspection failure appears across several installed panels. What is the best management response?

  • AIncrease every torque value above the manufacturer instruction
  • Contain, correct, and verify the root cause
  • CCorrect only the one panel the inspector opened
  • DCover the remaining panels before inspection

Why B is correct

A repeated defect indicates a process problem rather than one isolated punch item. Containment, root-cause analysis, retraining or tool correction, reinspection, and documented verification reduce recurrence while preserving listed installation requirements.

5. A drawing dimension conflicts with the specification. What is the defensible response?

  • Request clarification before affected work
  • BChoose the cheaper interpretation silently
  • CBuild both versions without authorization
  • DErase the specification requirement

Why A is correct

A written RFI identifies the conflict, preserves design responsibility, and lets cost or time consequences enter change control. Silent interpretation can produce nonconforming work.

6. Which package best supports electrical project closeout?

  • AOnly the final invoice
  • BUnmarked bid drawings only
  • CA verbal statement that systems operate
  • Tests and closeout records

Why D is correct

Closeout must demonstrate acceptance and provide the owner with usable operating and maintenance information. Billing alone does not document testing, configuration, or warranty obligations.

4 more in the bank

Answers and explanations for these are in the app.

  • The bid reconciliation shown identifies firestopping in the specification but not the estimate. What should the project manager do before contract execution?
  • Field installation begins before a required equipment submittal is approved. What is the main risk?
  • A four-person electrical crew is scheduled for three 8-hour days. How many labor-hours belong in the estimate?
  • An estimate carries 250 feet of conductor at $3.20 per foot. What material extension results before waste and tax?

Practice all 12 Project Design & Management questions