A late switchgear delivery affects an activity on the project critical path. What should the manager do first?

NASCLA Electrical exam practice question · Project Design & Management

A late switchgear delivery affects an activity on the project critical path. What should the manager do first?

  • ADelete required testing
  • BInstall unapproved equipment
  • Quantify and mitigate impact
  • DHide the delay until installation

Why C is correct

A critical-path delay can move project completion. The manager should update schedule logic, evaluate compliant alternatives, communicate impacts, and obtain approvals instead of concealing the constraint.