A late switchgear delivery affects an activity on the project critical path. What should the manager do first?
- ADelete required testing
- BInstall unapproved equipment
- Quantify and mitigate impact
- DHide the delay until installation
Why C is correct
A critical-path delay can move project completion. The manager should update schedule logic, evaluate compliant alternatives, communicate impacts, and obtain approvals instead of concealing the constraint.