Approved switchgear has a lead time longer than the current installation milestone. What is the best first project-control response?

NASCLA Electrical exam practice question · Project Design & Management

Approved switchgear has a lead time longer than the current installation milestone. What is the best first project-control response?

  • AHide the lead time until the milestone is missed
  • BOrder unapproved equipment with no submittal
  • CRemove testing activities to recover every lost day
  • Document constraints and update project logic

Why D is correct

A long-lead constraint belongs in the risk, procurement, and schedule processes. The manager should surface it, evaluate compliant mitigation, obtain approvals, and update dependencies; concealment or unauthorized substitution creates larger technical and contractual failures.