A drawing dimension conflicts with the specification. What is the defensible response?
- Request clarification before affected work
- BChoose the cheaper interpretation silently
- CBuild both versions without authorization
- DErase the specification requirement
Why A is correct
A written RFI identifies the conflict, preserves design responsibility, and lets cost or time consequences enter change control. Silent interpretation can produce nonconforming work.