A drawing dimension conflicts with the specification. What is the defensible response?

NASCLA Electrical exam practice question · Project Design & Management

A drawing dimension conflicts with the specification. What is the defensible response?

  • Request clarification before affected work
  • BChoose the cheaper interpretation silently
  • CBuild both versions without authorization
  • DErase the specification requirement

Why A is correct

A written RFI identifies the conflict, preserves design responsibility, and lets cost or time consequences enter change control. Silent interpretation can produce nonconforming work.