1. On a community-center project during plan review, a long exposed PVC raceway crosses a large temperature range; what should the installer evaluate?

  • AFilling joints with concrete
  • BOnly voltage drop
  • CRemoval of supports
  • Thermal expansion fittings

Why D is correct

PVC changes length significantly with temperature; accommodating movement prevents buckling and stress at enclosures. The best answer is therefore “Thermal expansion and the need for listed expansion fittings.” The other choices either address a different system, rely on an unsafe shortcut, or make a conclusion not supported by the stated facts.

2. On a single-family remodel during rough-in, a raceway penetration is made through a rated wall; how should it be closed?

  • ABy leaving an air gap
  • A matching firestop system
  • CWith ordinary painter's caulk
  • DWith loose insulation

Why B is correct

Rated assemblies depend on tested penetration details; generic filler does not demonstrate equivalent fire resistance. The best answer is therefore “With an approved firestop system installed for the specific assembly and penetration.” The other choices either address a different system, rely on an unsafe shortcut, or make a conclusion not supported by the stated facts.

3. Why must device yokes and internal clamps be included in box fill?

  • AThey eliminate grounding
  • They occupy specified conductor-volume allowances
  • CThey change circuit voltage
  • DThey increase breaker poles

Why B is correct

The box-fill rule accounts for items that consume wiring space or crowd conductors, including yokes, clamps, and grouped equipment grounds. Counting insulated conductors alone can overfill the box.

4. A raceway crosses a structural expansion joint. What must be coordinated?

  • ARigid attachment on both sides only
  • BRemoval of bonding
  • CA hidden splice at the joint
  • A listed movement provision and grounding continuity

Why D is correct

Structural movement can break raceway or pull conductors. Listed expansion or deflection fittings, correct setting, support, and bonding accommodate movement while maintaining the fault path.

12 more in the bank

Answers and explanations for these are in the app.

  • Using the raceway schedule shown, what information controls whether the added conductors fit?
  • The route diagram shows four 90-degree bends between pull points. What should be added or changed?
  • On a hotel renovation during plan review, raceway outdoors contains insulated conductors marked only for dry locations; what is the issue?
  • On a tenant improvement during rough-in, cable is draped across ceiling-grid wires that are not identified for electrical support; what is required?
  • On a restaurant build-out during rough-in, metal raceway is planned in a highly corrosive process area; what must be considered?
  • On a small hospital renovation during rough-in, a conductor splice is proposed inside a raceway body not marked with sufficient volume; what is the correct approach?
  • What information controls pull-box dimensions for large conductors?
  • A cable is proposed in tray but is not identified for that use. Is it acceptable?
  • A metal raceway fitting is not identified for grounding continuity. What is required?
  • A raceway route is made shallower than planned by final grading. What should be checked?
  • Long vertical conductors place excessive weight on terminations. What is required?
  • Flexible cord is routed through a wall as permanent branch wiring. What is the issue?

Practice all 16 Wiring Methods & Materials questions

Plus timed mock exams and a wrong book that follows you between the web and the app.

Start studying free

Other NASCLA Electrical content areas