1. A maintenance point can be energized by either a utility supply or a generator. What must be addressed before exposed electrical parts can be worked as deenergized?
- Lock out every source and verify
- BOpen only the utility breaker
- CPress STOP and rely on the pilot light
- DBegin after the generator engine stops
Where to look it up
https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.333
Why A is correct
Identify and isolate all sources, control stored energy, apply the required lockout/tagout procedure and have a qualified person verify the deenergized condition, including possible backfeed. A STOP button, stopped engine or opening only one source is insufficient.