EstatePass
Business & FinanceRegulationshard15% of exam part

On a job with a s. 713.23 payment bond, when must a lienor not in privity with the contractor serve its notice on the contractor?

Correct Answer

A) Before beginning, or within 45 days after beginning, to furnish labor, materials, or supplies

Section 713.23(1)(c): "Before beginning or within 45 days after beginning to furnish labor, materials, or supplies, a lienor who is not in privity with the contractor, except a laborer, shall serve the contractor with notice in writing that the lienor will look to the contractor’s bond for protection on the work." The 45 days mirrors the notice to owner on an unbonded job, which is why the two are easy to run together — but this one goes to the contractor and points at the bond.

Answer Options
A
Before beginning, or within 45 days after beginning, to furnish labor, materials, or supplies
B
Within 90 days after final furnishing, which is the same deadline as a recorded claim of lien
C
Within 15 days after the bond is recorded
D
Within 1 year after the last day on the job

Why This Is the Correct Answer

Section 713.23(1)(c): "Before beginning or within 45 days after beginning to furnish labor, materials, or supplies, a lienor who is not in privity with the contractor, except a laborer, shall serve the contractor with notice in writing that the lienor will look to the contractor’s bond for protection on the work." The 45 days mirrors the notice to owner on an unbonded job, which is why the two are easy to run together — but this one goes to the contractor and points at the bond.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.