EstatePass
Contract AdminContractsmedium40% of exam part

Before substantial completion, the architect rejects nonconforming tile. What AIA A201 duty follows?

Correct Answer

B) Correct rejected work

A201 requires correction of rejected or nonconforming Work.

Answer Options
A
Wait until final payment before correction
B
Correct rejected work
C
Ask the low bidder to approve the tile
D
Treat rejection as a bid addendum

Why This Is the Correct Answer

A201 requires correction of rejected or nonconforming Work.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.