The owner wants employees to occupy after cleaning but before official approval. What should be confirmed?

Correct Answer

B) Confirm CO or occupancy approval

FBC Chapter 1 governs occupancy approval.

Answer Options
A
Final subcontractor invoice
B
Confirm CO or occupancy approval
C
Original estimate summary
D
Punch-list subject line

Why This Is the Correct Answer

FBC Chapter 1 governs occupancy approval.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.