Before reviewing monthly pay applications, the architect requests an approved cost breakdown. Which AIA A201 tool is this?

Correct Answer

D) Schedule of Values

A201 uses a schedule of values as the basis for payment applications.

Answer Options
A
Notice of termination
B
Bid bond form
C
Shop drawing sample
D
Schedule of Values

Why This Is the Correct Answer

A201 uses a schedule of values as the basis for payment applications.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.