The architect sees defective work and unresolved lien exposure in a pay application. Which AIA A201 concept may justify reducing certification?

Correct Answer

B) Withholding certification to protect the Owner

A201 identifies grounds for withholding certification when needed to protect the Owner.

Answer Options
A
Automatic full certification because work has been billed
B
Withholding certification to protect the Owner
C
Bid-security release because a pay application was submitted
D
Owner financing evidence as the only payment control

Why This Is the Correct Answer

A201 identifies grounds for withholding certification when needed to protect the Owner.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.