Contract AdminContractsmedium40% of exam part

A trade claims the architect's submittal review approved a deviation never identified in writing. Which AIA A201 principle applies?

Correct Answer

A) Submittal review has limited effect

A201 limits submittal review and requires deviations to be identified through the proper process.

Answer Options
A
Submittal review has limited effect
B
Review automatically approves hidden deviations
C
Owner occupancy converts deviations into approved changes
D
Supplier transmittals amend the contract by themselves

Why This Is the Correct Answer

A201 limits submittal review and requires deviations to be identified through the proper process.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.