EstatePass
Contract AdminContractsmedium40% of exam part

A trade wants to install a lower-grade component that does not meet the specification. Which AIA A201 obligation applies?

Correct Answer

C) Provide required labor and materials

A201 requires the Contractor to provide materials and services required for proper execution of the Work.

Answer Options
A
Use the lowest available product whenever a quote is cheaper
B
Let the permit reviewer approve a private product substitution
C
Provide required labor and materials
D
Treat product quality as only a post-warranty issue

Why This Is the Correct Answer

A201 requires the Contractor to provide materials and services required for proper execution of the Work.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.