Contract AdminProceduresmedium13% of exam part

A submittal is rejected, but the trade wants to order material. What should the GC do?

Correct Answer

C) Hold rejected submittal item

Rejected submittals do not release procurement or installation.

Answer Options
A
Order from rejected submittal
B
Use invoice as approval
C
Hold rejected submittal item
D
Close the log without comments

Why This Is the Correct Answer

Rejected submittals do not release procurement or installation.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.