Contract AdminContractsmedium40% of exam part

A subcontractor asks for final payment before its closeout documents and required corrections are complete. Which AIA A401 area should the GC review?

Correct Answer

D) Subcontract final-payment requirements

A401 includes subcontract progress and final payment requirements tied to completion and required submissions.

Answer Options
A
A701 bidder representations before award
B
A201 owner financing evidence, without preserving the notice step that controls the remedy
C
A201 architect rejection of owner work
D
Subcontract final-payment requirements

Why This Is the Correct Answer

A401 includes subcontract progress and final payment requirements tied to completion and required submissions.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.