Newly installed equipment is not new and does not conform to the Contract Documents. Which AIA A201 obligation is most directly triggered?

Correct Answer

D) The Contractor's warranty that materials and equipment are new and the Work conforms

A201 includes contractor warranty obligations for materials, equipment, and conformity of the Work.

Answer Options
A
The Owner's right to approve every supplier invoice before delivery, and use that shortcut to decide the equipment requirement, and rely on field convenience instead of contract administration
B
The bidder's acknowledgment of addenda before bids are opened, without preserving the architect's limited review role
C
The county clerk's duty to issue a certificate of substantial completion
D
The Contractor's warranty that materials and equipment are new and the Work conforms

Why This Is the Correct Answer

A201 includes contractor warranty obligations for materials, equipment, and conformity of the Work.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.