The estimator finds an arithmetic error before the bid receipt deadline. Under AIA A701, what path matters?

Correct Answer

D) Follow the permitted bid modification or withdrawal procedure before the deadline

A701 controls bid modification and withdrawal timing before bid receipt.

Answer Options
A
Wait until substantial completion to correct the bid number, while bypassing the contract path for claims and disputes
B
Use a pay application to change the sealed bid after opening, without separating design review from means-and-methods control
C
Ask a supplier to certify the corrected owner-contractor agreement
D
Follow the permitted bid modification or withdrawal procedure before the deadline

Why This Is the Correct Answer

A701 controls bid modification and withdrawal timing before bid receipt.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.