A Florida project has a drawing keynote that omits a specification requirement for sealant testing. Under AIA A201, what is the best contract-administration response?

Correct Answer

A) Read the documents together and seek interpretation if the requirement is unclear

A201 treats the Contract Documents as complementary and uses the contract process for interpretation.

Answer Options
A
Read the documents together and seek interpretation if the requirement is unclear
B
Let the field crew delete testing because the drawing note is shorter, and letting a supplier quote decide the owner-contractor issue
C
Ask the sealant supplier to issue the official contract interpretation
D
Treat testing as a warranty item that can be decided after final payment

Why This Is the Correct Answer

A201 treats the Contract Documents as complementary and uses the contract process for interpretation.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.