Contract AdminContractsmedium40% of exam part

A contractor wants the owner, not the architect, to certify payment because the owner is in a hurry. Which AIA A201 role controls?

Correct Answer

D) Architect administration of the contract, including payment certification

A201 gives the Architect contract-administration duties during construction, including payment certification.

Answer Options
A
Subcontractor unilateral certification of the prime pay application
B
Building official certification of private contract payment
C
Bidder certification before the contract is awarded, while leaving the architect's review role out of the record
D
Architect administration of the contract, including payment certification

Why This Is the Correct Answer

A201 gives the Architect contract-administration duties during construction, including payment certification.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.