An asphalt patch is 12,960 sf at 1.5 in compacted thickness. Using 110 lb per square yard per inch, how many tons are required?

Correct Answer

C) 119 tons

Convert square feet to square yards, apply pounds per square yard per inch, then convert to tons.

Answer Options
A
79 tons
B
107 tons
C
119 tons
D
238 tons

Why This Is the Correct Answer

Convert square feet to square yards, apply pounds per square yard per inch, then convert to tons.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.