Contract AdminContractsmedium40% of exam part

The GC finds an unknown abandoned fuel tank in an excavation area. It materially differs from expected conditions. What AIA A201 process should be started?

Correct Answer

B) Give contract notice for concealed or unknown conditions

A201 requires notice and evaluation for concealed or unknown conditions before adjustments are resolved.

Answer Options
A
Remove it without notice and claim extra payment at final completion, while relying on a meeting agenda instead of a contract instrument
B
Give contract notice for concealed or unknown conditions
C
Treat it as a bid addendum even though bids are closed
D
Ask the lowest earthwork bidder to decide the owner adjustment

Why This Is the Correct Answer

A201 requires notice and evaluation for concealed or unknown conditions before adjustments are resolved.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.