An owner representative tells the GC exactly how to sequence temporary shoring. What AIA A201 contractor responsibility should the GC protect?
Correct Answer
B) Responsibility for construction means, methods, techniques, sequences, and procedures
A201 generally keeps means and methods responsibility with the Contractor.
Why This Is the Correct Answer
A201 generally keeps means and methods responsibility with the Contractor.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The parties cannot resolve the dispute after mediation. Which AIA A201 topic points to the next forum if selected in the agreement?
Next Question
The GC finds an unknown abandoned fuel tank in an excavation area. It materially differs from expected conditions. What AIA A201 process should be started?
