An owner representative tells the GC exactly how to sequence temporary shoring. What AIA A201 contractor responsibility should the GC protect?

Correct Answer

B) Responsibility for construction means, methods, techniques, sequences, and procedures

A201 generally keeps means and methods responsibility with the Contractor.

Answer Options
A
The Owner's exclusive right to direct all field techniques after financing is shown
B
Responsibility for construction means, methods, techniques, sequences, and procedures
C
The building official's duty to supervise daily contractor labor production
D
The supplier's authority to issue binding interpretations of design intent, while making a field preference override the written process

Why This Is the Correct Answer

A201 generally keeps means and methods responsibility with the Contractor.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.