A subcontractor expects immediate payment after sending an invoice, even though the prime contract payment cycle has not run. Which AIA A401 area should the GC review?

Correct Answer

D) Subcontract progress-payment and final-payment provisions tied to the subcontract documents

A401 includes subcontract payment provisions that must be administered through the subcontract relationship.

Answer Options
A
Bid-security forfeiture rules used before the subcontract is awarded
B
Architect final-completion certification for unrelated owner work, and close the issue in the estimator's pricing notes
C
Owner financing evidence requested before the subcontractor prices the scope
D
Subcontract progress-payment and final-payment provisions tied to the subcontract documents

Why This Is the Correct Answer

A401 includes subcontract payment provisions that must be administered through the subcontract relationship.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.