The owner asks whether the Contract Time includes the date by which Substantial Completion must be achieved. Where is this concept handled?

Correct Answer

C) AIA A201 Article 8 provisions for time and progress

A201 Article 8 addresses Contract Time, progress, and completion timing.

Answer Options
A
AIA A701 bid security forfeiture provisions only
B
Use AIA A401 subcontract invoicing provisions to define the prime Contract Time milestone
C
AIA A201 Article 8 provisions for time and progress
D
AIA A201 final payment release provisions only

Why This Is the Correct Answer

A201 Article 8 addresses Contract Time, progress, and completion timing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.