The contractor repeatedly fails to supply enough properly skilled workers and materials. What AIA A201 owner remedy may apply if procedures are satisfied?

Correct Answer

B) Termination by the Owner for cause

A201 Article 14 includes termination by the Owner for cause based on specified grounds and procedures.

Answer Options
A
Bid modification before bid opening, and use that shortcut to decide the termination for cause requirement, and let the vendor's delivery date control the contract duty
B
Termination by the Owner for cause
C
Submittal approval by a supplier
D
Final payment without correction

Why This Is the Correct Answer

A201 Article 14 includes termination by the Owner for cause based on specified grounds and procedures.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.