A material quote expires before the owner will award the contract. What should the estimator do?

Correct Answer

A) Carry or qualify the escalation risk instead of assuming the quote will remain valid

Preconstruction pricing should account for quote validity and escalation risk.

Answer Options
A
Carry or qualify the escalation risk instead of assuming the quote will remain valid
B
Use the expired quote without disclosure because it was the first number received
C
Make the supplier responsible for all future price changes without written agreement
D
Treat the expiration as an automatic deduct alternate

Why This Is the Correct Answer

Preconstruction pricing should account for quote validity and escalation risk.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.