Contract AdminContractsmedium40% of exam part

Waste from the GC's operations is blocking an occupied corridor next to the work area. Which AIA A201 duty is most directly involved?

Correct Answer

B) Keep the premises and surrounding area free from waste materials and rubbish caused by operations

A201 includes a contractor duty to keep the site and surrounding area free of waste and rubbish caused by operations.

Answer Options
A
Wait until final completion before removing any construction waste, while making a field preference override the written process
B
Keep the premises and surrounding area free from waste materials and rubbish caused by operations
C
Make the architect responsible for jobsite housekeeping after each visit, and use that shortcut to decide the area from operations requirement, and let the lowest trade proposal control the answer
D
Bill cleanup only to the lender because the owner uses the corridor

Why This Is the Correct Answer

A201 includes a contractor duty to keep the site and surrounding area free of waste and rubbish caused by operations.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.