After substantial completion, a defect appears during the correction period. Which AIA A201 topic should the GC check?

Correct Answer

B) Correction of Work after Substantial Completion

A201 includes correction obligations after Substantial Completion, commonly associated with the correction period.

Answer Options
A
Bid withdrawal before receipt of bids, which does not address post-occupancy defects
B
Correction of Work after Substantial Completion
C
Owner financing evidence before award, unrelated to correcting defective work after occupancy
D
Subcontractor listing in the bid form, not the correction-period duties after Substantial Completion

Why This Is the Correct Answer

A201 includes correction obligations after Substantial Completion, commonly associated with the correction period.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.