The GC receives a cheaper product proposal that does not satisfy the specified performance criteria. Which AIA A201 contractor duty controls the response?

Correct Answer

C) Provide labor, materials, equipment, and services required for proper execution of the Work

A201 requires the Contractor to provide the labor and materials required by the Contract Documents.

Answer Options
A
Use the lowest-cost product whenever it improves bid-day margin, and omit the issue from the current contract-administration log
B
Shift specified performance to the payment bond surety after award
C
Provide labor, materials, equipment, and services required for proper execution of the Work
D
Treat every substitution as approved if the supplier can ship quickly

Why This Is the Correct Answer

A201 requires the Contractor to provide the labor and materials required by the Contract Documents.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.