Contract AdminPermitsmedium20% of exam part

The owner wants to occupy a newly improved space after cleaning but before official occupancy approval. Which FBC topic controls?

Correct Answer

B) Certificate of occupancy or required occupancy approval

FBC Chapter 1 controls occupancy approval through certificates or required approval.

Answer Options
A
The final subcontractor invoice
B
Certificate of occupancy or required occupancy approval
C
The original estimate summary
D
The punch-list email subject line

Why This Is the Correct Answer

FBC Chapter 1 controls occupancy approval through certificates or required approval.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.