Contract AdminContractsmedium40% of exam part

The site survey supplied by the owner conflicts with civil drawings. Under AIA A201, which owner-side contract area is involved?

Correct Answer

A) Information and services required of the Owner, including site information needed for the Work

A201 places certain project information and services, such as surveys, in the Owner article.

Answer Options
A
Information and services required of the Owner, including site information needed for the Work
B
The Contractor's duty to clean up rubbish caused by its own operations, and use that shortcut to decide the site requirement, while turning a quality issue into a bid-security issue
C
Bid security forfeiture if the selected bidder refuses to sign the agreement
D
A subcontractor's progress-payment timing after a monthly invoice, and let the permit reviewer resolve the private contract issue

Why This Is the Correct Answer

A201 places certain project information and services, such as surveys, in the Owner article.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.