Weather and an owner-directed sequence change affect the critical path. Under AIA A201, what must the GC generally do to pursue more time?

Correct Answer

D) Use the contract claim or change process for an extension of Contract Time

A201 handles extensions of Contract Time through the contract's delay, change, and claim procedures.

Answer Options
A
Assume every critical-path delay grants extra time without notice, analysis, or a claim
B
Wait until final payment and revise the bid form instead of documenting the delay claim
C
Ask a material supplier to certify substantial completion for the time-extension request
D
Use the contract claim or change process for an extension of Contract Time

Why This Is the Correct Answer

A201 handles extensions of Contract Time through the contract's delay, change, and claim procedures.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.